A 2,800 MW coal-fired power plant in Georgia purchased more than $1 million in industrial air-dryer equipment — then discovered during installation planning that the new dryers had a significantly larger footprint than the equipment they replaced. They wouldn’t fit the existing compressor room, the infrastructure changes to make room threatened to exceed $1 million on their own, and the work had to happen inside a scheduled outage with little time to redesign.

The approach

power plant reality capture asbuiltasbuilt reality capture power plant

AsBuilt — Acensium’s scan-and-model division — captured the entire 5,000-square-foot compressor room with FARO laser scanning at 2 mm accuracy and sub-millimeter point spacing, collecting more than 20 billion points into a high-fidelity 3D digital twin. Acensium engineers used that model to test six different equipment layouts virtually, then developed a revised P&ID and fabrication-ready shop drawings — resolving the fit before any steel or pipe was cut.

What we delivered

asbuilt 3d model power plant

asbuilt 3d model power plant

  • High-density point-cloud dataset and Navisworks coordination model
  • Revit 3D model with tagged equipment and a custom P&ID
  • AutoCAD DWG package: general arrangement, equipment elevations, and pipe-spool fabrication drawings
  • Post-installation as-built documentation

Results

  • $1M+ investment preserved — the purchased dryers were made to fit without a costly room rebuild.
  • $60,000+ in field labor avoided — shifted to shop fabrication against verified dimensions.
  • Finished a week early — installation completed ahead of the planned schedule.
  • Zero downtime, zero rework — every fabricated component matched the design on the first fit.

Why it matters

The most expensive place to discover a fit problem is the field, mid-outage. A verified digital twin let Acensium prove the layout — six ways — before installation, turning a potential seven-figure overrun into an on-time, no-downtime retrofit.